Alliance Recovery Corporation (ARVY.OB) Commencing Engineering Activities

The Company remains committed to the outsourcing engineering, scientific and technical expertise that is required for the initial “waste to energy” installation. It is the Company’s opinion that it is much more cost effective to outsource the wide range of required expertise rather than creating a similar technical and scientific group within the Company’s management group.

We are pleased to announce that Resource International of Ashland, Virginia (www.resourceintl.com/index.htm) has been selected as the consulting engineers that will provide the overall project management for the Company’s initial “waste to energy” processing facility. Resource International will bring both project specific engineers and scientists into the Alliance team. This expertise is a welcomed addition to the management team responsible for the planning, design, fabrication, installation and operation of Alliance’s initial “waste to energy” installation.

Commencing work March 14, 2007, initially the Alliance engineering team headed up by Resource International and comprised of Alliance management, Resource consulting engineers, and fabrication experts, will begin by reviewing a contract that will provide for the scope of engineering activities necessary complete the entire facility. Resource International will be responsible for overall project management of the entire “waste to energy” installation.

Although process design parameters have been established previously, the engineering team will be working with pre-qualified suppliers to examine the possibility to enhance the commercially available process components to take advantage of the latest technological advances related to fabrication methods, materials and controls. All of the equipment that will be utilized in the Alliance process is currently in use in chemical processing and related industries.

The Alliance engineering team will be integrating existing equipment as the system’s components to obtain the desired results for the final Alliance process. As an example, the entire electrical generation system is purchased as a stand-alone system. It will be necessary to integrate the electrical generation system’s heat recover process into facility’s central heat recovery system.

Resource will also bring civil, mechanical, chemical and process engineers into the Alliance project management team. This group of engineers within Resource’s organization, has acquired specific knowledge pertaining the to the Alliance system as a result of working closely with Alliance management for several years. As the engineering team finalizes fabrication designs, or makes equipment modifications, develops control software, and/or makes any proprietary enhancements to the Company’s technology, they will seek various forms of additional intellectual property protection including patents and industrial designs that will be owned by Alliance.

The Company and Resource are also prepared to continue discussions with state and municipal officials in connection to final site selection. Several locations have been identified. Although some discussions with state and regulatory officials have already been initiated, the Company and their engineers will expand these discussions to include additional municipalities and continue to work through the assessment process prior to making a determination as to the best location for the initial Alliance “waste to energy” processing facility to operate.

Archives

Select A Month
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • December 2023
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • January 2023
  • December 2022
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • February 2021
  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • August 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • February 2019
  • January 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
  • August 2018
  • July 2018
  • June 2018
  • May 2018
  • April 2018
  • March 2018
  • February 2018
  • January 2018
  • December 2017
  • November 2017
  • October 2017
  • September 2017
  • August 2017
  • July 2017
  • June 2017
  • May 2017
  • April 2017
  • March 2017
  • February 2017
  • January 2017
  • December 2016
  • November 2016
  • October 2016
  • September 2016
  • August 2016
  • July 2016
  • June 2016
  • May 2016
  • April 2016
  • March 2016
  • February 2016
  • January 2016
  • December 2015
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • May 2015
  • April 2015
  • March 2015
  • February 2015
  • January 2015
  • December 2014
  • November 2014
  • October 2014
  • September 2014
  • August 2014
  • July 2014
  • June 2014
  • May 2014
  • April 2014
  • March 2014
  • February 2014
  • January 2014
  • December 2013
  • November 2013
  • October 2013
  • September 2013
  • August 2013
  • July 2013
  • June 2013
  • May 2013
  • April 2013
  • March 2013
  • February 2013
  • January 2013
  • December 2012
  • November 2012
  • October 2012
  • September 2012
  • August 2012
  • July 2012
  • June 2012
  • May 2012
  • April 2012
  • March 2012
  • February 2012
  • January 2012
  • December 2011
  • November 2011
  • October 2011
  • September 2011
  • August 2011
  • July 2011
  • June 2011
  • May 2011
  • April 2011
  • March 2011
  • February 2011
  • January 2011
  • December 2010
  • November 2010
  • October 2010
  • September 2010
  • August 2010
  • July 2010
  • June 2010
  • May 2010
  • April 2010
  • March 2010
  • February 2010
  • January 2010
  • December 2009
  • November 2009
  • October 2009
  • September 2009
  • August 2009
  • July 2009
  • June 2009
  • May 2009
  • April 2009
  • March 2009
  • February 2009
  • January 2009
  • December 2008
  • November 2008
  • October 2008
  • September 2008
  • August 2008
  • July 2008
  • June 2008
  • May 2008
  • April 2008
  • March 2008
  • February 2008
  • January 2008
  • December 2007
  • November 2007
  • October 2007
  • September 2007
  • August 2007
  • July 2007
  • June 2007
  • May 2007
  • April 2007
  • March 2007
  • February 2007
  • January 2007
  • December 2006
  • November 2006
  • October 2006
  • September 2006
  • August 2006
  • July 2006
  • June 2006
  • May 2006
  • April 2006
  • March 2006
  • January 2006
  • December 2005
  • October 2005
  • September 2005
  • Market Basics

    New to the micro-cap markets?Get answers to your questions about investing in Small-Cap / Micro-Cap Stocks and learn how to protect yourself.

    The Basics

    Newsletter Publishers

    Have an up and coming newsletter and want to be included in our coverage list? Looking to get more coverage and grow subscriptions? Register for coverage.

    Register

    Public Companies

    Are you a Small-Cap / Micro-Cap company looking for coverage? We'd love to hear from you. Fill out our quick contact form or send us a text.

    Get Covered